Subscribe

Climate Action Delays Pushing Up Electricity Costs

/ 15th October 2021 /
Ed McKenna

Failures to implement key actions from the government’s 2019 Climate Action Plan are contributing to concerns over energy shortages and will delay reaching decarbonisation targets.

That’s according to the Irish Solar Energy Association, which says that only three out of 18 key actions identified for the electricity sector have been implemented substantially or fully. Published in June 2019, the CAP listed 183 actions including 18 relating to the electricity sector, with three now largely complete, nine recording ‘work ongoing’, and six showing no or minimal progress.

Chief executive Conall Bolger (pictured) told the association’s annual conference:  “The 2019 Climate Action Plan was an ambitious undertaking and charted a positive course for Ireland to meaningfully address the climate crisis. It was abandoned earlier this year in favour of a new set of interim climate actions, which will soon be surpassed by yet another new Climate Action Plan.

“Continuously unveiling rehashed plans may make for good headlines but they mean nothing without implementation. 

“Reviewing progress towards the original 2019 actions has revealed a worrying lack of progress. By delivering just one in six actions we are simply not making sufficient progress as a country. This is now having a real impact on households across Ireland, as our continued reliance on fossil fuels is driving increased electricity prices.”

In Association with

He called for the government and relevant bodies to prioritise several actions that could have a substantial impact.

“Important for hard hit consumers is the introduction of a Microgeneration Support Scheme (Action 30, due Q2 2021) to encourage households to generate their own clean energy. A scheme allowing those who invest in technologies such as rooftop solar panels to sell excess power to the national grid would make an immediate impact. ISEA estimate that this could deliver 1GW of solar power per year by the end of this decade.”

While at least one electricity supplier is paying for customer-generated electricity, the general scheme, due to be implemented by June 30 this year, has not materialised.

RESS Delay

Bolger said the single biggest climate change failure of this government was the delay in the RESS 2 auction, due this year but postponed to Q3 2022. 

“The Renewable Electricity Support Scheme was supposed to be an annual process to provide financial support to renewable electricity projects in Ireland, but the 2021 auction was cancelled without explanation. This will delay, by at least a year, the introduction of new renewable electricity sources to the national grid at a time when we can least afford to.” 

He added that easing restrictions on private networks (Action 22, due Q4 2021) would be a significant benefit, particularly for large energy users. Such networks allow large industrial users of electricity to generate their own renewable electricity in a separate location and transmit the energy directly, rather than through the national grid.

“Private networks are commonplace in many other countries. They speed up the delivery of renewables, reduce the associated costs while also reducing the pressures on the national grid. Unfortunately, Irish regulations continue to prevent them,” concluded Bolger. 

The full list of actions in the Climate Action Plan 2019 is available here.

ISEA’s Analysis of the Climate Action Plan 2019 

Action

Due

Lead organisation

Status

16. We will require, at scale, electricity/gas providers to provide detail on energy use and potential energy savings, for instance as part of consumers bills

Q2 2020

DCCAE

Complete

17. Ensure that ESB Networks and EirGrid plan network and deliver on connecting renewable energy sources to meet the 2030 70% RES-E target

Q1 2021

ESBN, EirGrid

Complete

18. Facilitate additional hybrid connections (e.g. solar/wind/batteries) operating in the electricity market to increase RES-E penetration

Q3 2021

CRU, DCCAE

Overdue

19. Ensure that the next phase of renewable connection policy is fit for purpose to deliver on renewable energy targets and community projects, and report annually on the timeliness of grid connection

2022 onwards

CRU, ESBN

Work completed to date is not fit for purpose

20. Implement energy actions under the Government Statement on the Role of Data Centres in Ireland’s Enterprise Strategy to ensure that large demand connections are regionally balanced to minimise grid reinforcements

2019-2022

EirGrid,CRU

Overdue

21. Ensure that updated planning guidelines for onshore wind are published in 2019

2019

DHPLG

Overdue

22. Further consider facilitation of private networks/direct lines

Q4 2021

CRU, DCCAE

Overdue

23. Assess the network development required to integrate higher levels of RES-E and develop a high-level network development plan to (and beyond) 2030

2020-2030

EirGrid, ESBN, CRU, DCCAE

On track

24. Facilitate very high penetration of variable renewable electricity by 2030 (both SNSP and average) through system services and market arrangements

Q4 2023

EirGrid, CRU

Behind schedule

25. Facilitate the development of Offshore Wind, including the connection of at least 3.5 GW of offshore wind, based on competitive auctions, to the grid by 2030. We will establish a top team to drive this ambition

2025

Multiple

Behind schedule

26. Support the ocean energy research, development and demonstration pathway for emerging marine technologies (wave, tidal, floating wind) and associated test infrastructure

Q4 2020

SEAI

Behind schedule

27. Support innovation enterprise hubs and the supply chain for offshore renewable energy

Q1 2021

SEAI, EI, DHPLG

Behind schedule

28. Design and implement the RESS. Increase the volumes and frequencies of RESS auctions to deliver on the 70% renewable electricity target by 2030 ensuring an appropriate community/enterprise mix to achieve an efficient delivery of renewables.

2022

DCCAE

Behind schedule

29. Ensure that 15% of electricity demand is met by renewable sources contracted under Corporate PPAs

Q4 2020

SEAI, DCCAE

Overdue

30. Develop an enabling framework for micro-generation which tackles existing barriers and establishes suitable supports within relevant market segments

Q2 2021

DCCAE, CRU, DHPLG

Overdue

31. Deliver pilot solar PV micro-generation scheme with a view to commencement of enduring support scheme by 2021, at the latest, to ensure that people can sell excess electricity they produce back to the grid

Q4 2019

SEAI, DCCAE

Behind schedule

32. Deliver Smart Metering Programme in line with current planned timelines that will support the market for micro-generation

Q3 2019

CRU, SEAI

Overdue

33. Establishment of a Steering Group to examine and oversee the feasibility of the utilisation of CCS in Ireland, and report to the Standing Committee on Climate Action as appropriate

Q3 2020

DCCAE

Behind schedule

 

Sign up to The Business Plus Panel to help shape the business decisions of tomorrow and win vouchers for your opinions! 
linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram